Activity - Gorgon Gas Development Gorgon Umbilical

Activity details
Organisation Chevron Australia Pty Ltd
Project
Activity types Construction and installation of a pipeline
Operation of a petroleum pipeline
In-force EP 7479
Submission date 27 June, 2023
Outcome Accepted
Acceptance date 17 January, 2024
Locations North West
Start date 29 February, 2024
Stop date Pending titleholder notification
Lifecycle Classification
Please note: activity start and stop dates are based on notifications provided by the titleholder.

Titleholder contact
Unavailable

Activity Description
Chevron Australia, on behalf of the Gorgon Joint Venture, operates the Gorgon Project (Gorgon) in Western Australia. Gorgon comprises offshore production wells and pipeline infrastructure that gathers natural gas from the Jansz–Io and Gorgon gas fields and transports it to a facility on Barrow Island for processing.

To support the reliability of the offshore gas gathering systems, Chevron Australia will install an additional control and electrical umbilical to the existing feed gas pipeline system that extends between the offshore Gorgon field and the facility on Barrow Island. Temporary power supply (e.g. via subsea batteries or a downline power cable) will be required during the transition from the use of the existing Gorgon umbilical to the additional control and electrical umbilical. If power supply from the existing umbilical becomes unavailable prior to the commissioning of the additional control and electrical umbilical, a temporary power supply may also be utilised to maintain electrical power supply.

The Gorgon gas field is located within production licences WA-37-L and WA-38-L, ~130 km off the north-west coast of Western Australia (WA), and ~65 km north-west of Barrow Island. The infrastructure to be installed under this Environment Plan (EP) will form part of pipeline licence WA-20-PL.

This EP documents the assessment and management of potential environmental impacts and risks associated with the installation of the additional umbilical bundle and the supply of temporary power in Commonwealth waters.

The scope of activities includes:
• Installation
• Inspection, maintenance and repairs
• Temporary power supply
• Field support.

Installation of the Gorgon umbilical is planned to occur from late 2023/early 2024 to mid-2024 and the total duration of activities is expected to be ~6 months.
Location map (click to enlarge)
Location map - Activity: Gorgon Gas Development Gorgon Umbilical (refer to description)

Accepted EP Documents

EP Document A1053821 (48.3 MB)
OPEP Document A947402 (2.7 MB)
OSMP Document A1022542 (18.5 MB)