Minerva Decommissioning and Field Management
| Activity type | Decommissioning, dismantling or removing a facility |
|---|---|
| Activity subtypes | |
| Lifecycle Classification | Decommissioning |
| Submitted by | Woodside Energy (Victoria) Pty Ltd |
| Submission date | 13 November, 2026 |
| Subtype | Revision |
| Decision date | |
| RMS ID | 9095 |
| Status | Under assessment (with NOPSEMA) |
| Link to previously accepted EP | 7780 - Minerva Decommissioning and Field Management |
| Contact |
Woodside Energy (Victoria) Pty Ltd, as titleholder under the Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2023 (Cth) (referred to as the Environment Regulations), proposes to undertake decommissioning activities within offshore petroleum production licence VIC/L22 and pipeline licence VIC/PL33.
The decommissioning activities include the removal of the Minerva pipeline and associated infrastructure, together with the ongoing field management activities associated with that infrastructure prior to decommissioning. Following decommissioning, environmental monitoring to support the eventual relinquishment of the production and pipeline licences will also be undertaken.
The Minerva field is located within permit area VIC/PL33 and VIC/L22, located in Commonwealth waters in the Otway Basin approximately 7 km south-southwest of Port Campbell, Victoria. The Minerva subsea infrastructure is in approximately 50–60 m water depth.
A single multipurpose construction vessel (MCV) is expected to be the only vessel required to remove the remaining Minerva subsea infrastructure and undertake field management activities and environmental surveys. Ad hoc support may be provided by a small local supply vessel with support vessel visits to the MCV expected to be infrequent and of short duration.
The infrastructure removal window is 1 September 2027 to 30 April 2028 with a cumulative duration of approximately 30 to 45 days. The infrastructure removal activity will not be undertaken outside this window. The environmental monitoring survey will be of approximately 5 days duration and commence after complete removal of the Minerva subsea infrastructure. The field management activities are ongoing from EP acceptance until the infrastructure is removed.
The Petroleum Activity may be undertaken 24 hours per day, seven days per week. Timing and duration may be subject to change due to project schedule requirements, vessel availability, unforeseen circumstances, and weather conditions.