Activity - North West Shelf Phase 1 Plug and Abandonment and TPA03 Well Intervention

Activity details
Organisation Woodside Energy Ltd
Project North West Shelf
Activity types Drilling
Any other petroleum-related activity
In-force EP 8208
Submission date 20 February, 2025
Outcome Accepted
Acceptance date 23 December, 2025
Locations North West
Start date 04 February, 2026
Stop date Pending titleholder notification
Lifecycle Classification Decommissioning
Please note: activity start and stop dates are based on notifications provided by the titleholder.

Titleholder contact
Nicolas Wirtz
Phone: 08 9348 4000

Activity Description
Woodside Energy Ltd (Woodside) proposes to undertake permanent plug and abandonment (P&A) and well intervention activities for subsea wells associated with the North West Shelf Development, as part of the Petroleum Activity under this Environment Plan (EP):
• P&A of three Angel field wells (AP2, AP3, and AP4) in production licence WA-3-L;
• P&A of two Perseus over Goodwyn (PoG) wells (PER-02, PER-04) in production licence WA-1-L;
• Well intervention activity on the TPA-03 well located in WA-5-L;
• inspection, maintenance, and repair (IMR) activities in preparation for plugging and abandonment of the wells listed above.

All wells are located in Commonwealth waters in the Northern Carnarvon Basin around Woodside’s existing production facilities. The closest well to shore is approximately 125 km north of Dampier. The wells are in water depths ranging from approximately 77 m to 128 m.

The plugging and abandonment and well intervention will be undertaken using a moored or hybrid (mooring and dynamic positioning capability) semi-submersible mobile offshore drilling unit (MODU), supported by vessels. The MODU will enter the operational area to undertake plug and abandonment activities, and be removed from the operational area once activities are complete. Vessels may undertake preparatory activities, such as pre-laying of moorings and preparation of subsea infrastructure, in addition to supporting the MODU.

The plug and abandonment activities (including preparation activities) are expected to require between 14 to 57 days to complete, subject to weather, vessel and MODU availability, or other unforeseen events. The Petroleum Activity is scheduled to occur between Q1 2026 and Q4 2026, with activities occurring 24 hours per day.

In the same MODU campaign, Woodside proposes to conduct well intervention activities at the TPA03 well to remediate a down-hole valve and continue production from the lower reservoir. Once the well intervention has been completed, the well will be shut-in until production is required. The shut-in and subsequent return to production of the well will be managed under the accepted Goodwyn Alpha (GWA) Facility Operations Environment Plan (March 2022) as part of ongoing operations. Well intervention activities at TPA03 are expected to require between 5 to 14 days to complete, subject to weather, vessel and MODU availability, or other unforeseen events.

This EP is not intended to be the final decommissioning EP for Woodside’s property in WA-1-L and WA-3-L, as such Section 270 of the OPGGS Act and title surrender requirements are not included in this EP.
Location map (click to enlarge)
Location map - Activity: North West Shelf Phase 1 Plug and Abandonment and TPA03 Well Intervention  (refer to description)

Accepted EP Documents

EP Document A1282745 (76.6 MB)
OSMP Document A1282743 (1.94 MB)