Activity - JUR Drilling

Activity details
Organisation Esso Australia Resources Pty Ltd
Project Bass Strait Development
Activity types Drilling
Construction and installation of a facility
In-force EP 4944
Submission date 09 August, 2019
Outcome Accepted
Acceptance date 08 January, 2020
Locations Gippsland
Start date 10 January, 2020
Stop date 13 April, 2020
Lifecycle Classification Development
Please note: activity start and stop dates are based on notifications provided by the titleholder.

Titleholder contact
Louise Mayboehm
Phone: +61 3 9261 0263

Activity Description
The West Barracouta (BTW) and Kipper (KPA) drilling campaigns will utilise the Noble Tom Prosser Jack Up Rig to drill a total of four subsea production gas wells, two at each location. The BTW campaign will take place in Production Licence VIC/L1 located in the Gippsland Basin of eastern Bass Strait 6 km south west of the Barracouta Platform, approximately 30 km off the coast in 45.5 m of water depth. The KPA campaign will take place in VIC/L25 at the Kipper Subsea Facility approximately 45 km off the coast in 95 m of water depth. Drilling activity is expected to commence in 1Q2020 and be completed no later than 4Q 2021, with each well taking 50-80 days to drill.
Location map (click to enlarge)
Location map - Activity: JUR Drilling (refer to description)

Accepted EP Documents

EP Document A710179 (79.9 MB)