Banner image

Gippsland Offshore Operations

Activity type Operation of a petroleum pipeline
Activity subtypes Any other petroleum-related activity
Lifecycle Classification Operation & Production
Submitted by Cooper Energy (PBF) Pty. Ltd.
Submission date 07 February, 2024
Subtype Revision
Decision date
RMS ID 7730
Status Under assessment (with titleholder)
Link to previously accepted EP 4705 - Gippsland Offshore Operations
Contact
Chad Wilson
Phone: 8100 4900
Location map (click to enlarge)
Location map - Activity: Gippsland Offshore Operations (refer to description)
Description

Cooper Energy Limited (Cooper Energy) holds a 100% interest and is the operator of the Gippsland Offshore Operations assets off Victoria’s south-west coast within the following Licence areas:
• Patricia Baleen gas field and associated infrastructure in VIC/L21, 25 km south of Marlo, and associated pipeline and umbilical (VIC/PL31 and VIC/PL31(V)) to the Orbost Gas Plant; and
• Sole gas field and associated infrastructure in VIC/L32, 40 km south of Bemm River, and associated pipeline and umbilical (VIC/PL43 and VIC/PL006401(V) to the Orbost Gas Plant.

The Gippsland Offshore Operations fields and associated infrastructure are in Commonwealth waters and the Patricia Baleen and Sole pipeline and umbilicals are within Commonwealth and State waters. Water depths across the Gippsland Offshore Operations assets range from 9 m to 125 m.

This Environment Plan (EP) is submitted as a 5-year revision of the Gippsland Offshore Operations EP.
The scope of the activities related to the Gippsland Offshore Operations and covered by this EP are:

Operation of the Sole gas field consisting of the following infrastructure (24/7, 365-days a year):
- The Sole-3 and Sole-4 production wells;
- A 65 km subsea pipeline and umbilical connecting the Sole-3 and Sole-4 wells to the Orbost Gas Plant; and
- Sole-2 wellhead
Non-productive phase of the Patricia Baleen fields and associated shut-in infrastructure consisting of:
- The Patricia-2 and Baleen-4 wells;
- A 24 km subsea pipeline and umbilical cable connecting the Patricia-2 and Baleen-4 wells to the Patricia Baleen Gas Plant; and
- Patricia-1 suspended well.

Inspection, maintenance and repair activities on the Patricia Baleen and Sole infrastructure from Dive support or Construction support vessels with ROV. Indicatively, vessel-based IMR activities are expected to occur every 1-2 years, and may have a duration of between 2-4 weeks, up to ~8 weeks in the unlikely case that a major repair is required.

Other Details
Locations Gippsland
Commonwealth waters adjacent to VIC
Titles (or other instruments) VIC/RL16
VIC/L32
VIC/PL31
VIC/PL43
Current Documents (Under assessment)
EP Document


OPEP Document


OSMP Document


Location map