Banner image

BTW Installation, Commissioning and Initial Operations

Activity type Significant modification of a petroleum pipeline
Activity subtypes
Lifecycle Classification Development
Submitted by Esso Australia Resources Pty Ltd
Submission date 16 October, 2020
Subtype Revision
Decision date 17 December, 2020
RMS ID 5415
Status Finalised
Outcome Accepted
Link to previously accepted EP 5241 - BTW Installation, Commissioning and Initial Operations
Contact
Hena Kalam
Phone: (03) 9261 0000
Location map (click to enlarge)
Location map - Activity: BTW Installation, Commissioning and Initial Operations (refer to description)
Description

Esso has recently drilled and completed two subsea gas production wells in the West Barracouta (BTW) field in Production Licence VIC/L1 approximately 15km off the Gippsland coastline, south of Lakes Entrance in a water depth of 45m. At the completion of drilling the wells were suspended.

The BTW installation campaign includes:
• Installation of two subsea trees on the BTW wells.
• Laying a 6km long 12” flexible pipeline between the wells and the existing BTA450 pipeline to shore (Pipeline Licence VIC/PL1).
• Tie-in to the existing / operating BTA450 pipeline via a Hot Tap.
• Laying and trenching a control umbilical from the wells to the Barracouta (BTA) platform located in Production Licence VIC/PL2.
• Installation of associated subsea equipment including the Pipeline End Manifold (PLEM) and pipeline skid, Umbilical Termination Assembly (UTA) and jumpers and flying leads.
• Pre commissioning.

The installation activities will be undertaken by a Dive Support Vessel (DSV) utilising divers and remotely operated vehicles. The DSV will be operating in the BTA platform Petroleum Safety Zone (PSZ) when performing the hot tap operations and installing the umbilical to the platform. Activities around the BTW wells are located 6km distant from the platform and within the BTW PSZ. Diving operations will be supported by a Hyperbaric Rescue Vessel stationed outside the BTW PSZ. The activities will be undertaken in multiple stages and it is expected that the DSV will travel between the onshore supply base and BTW between each stage.

The earliest date of commencement of the installation campaign is late Q4 2020. Activities will be conducted 24 hours per day, seven days per week. It is expected to take approximately six weeks to complete the installation activity.

Following completion of the installation campaign the wells and pipeline will be commissioned and production will start-up. This revision is to address the commissioning and initial start-up stage, the installation activities were addressed in a previous submission that has already been accepted by NOPSEMA.

Other Details
Locations Gippsland
Commonwealth waters adjacent to VIC
Titles (or other instruments) VIC/PL1
VIC/L1
VIC/L2
Current Documents (Under assessment)
EP Document


Location map