Cobia Pipeline Repair Project

Activity type Significant modification of a petroleum pipeline
Activity subtypes
Lifecycle Classification Operation & Production
Submitted by Esso Australia Resources Pty Ltd
Submission date 17 July, 2018
Subtype New
Decision date 29 November, 2018
RMS ID 4564
Status Finalised
Outcome Accepted
Link to previously accepted EP
Contact

Carolyn Thomas
Risk, Environment and Regulatory Supervisor
Esso Australia Resources Pty Ltd
Level 9, 664 Collins Street
DOCKLANDS  VIC  3008
+61 3 9261 0260
carolyn.y.thomas@exxonmobil.com

Location map (click to enlarge)
Location map - Activity: Cobia Pipeline Repair Project (refer to description)
Description


The Cobia Pipeline Repair Project Environment Plan covers the repair of the existing 300mm pipeline between the Halibut and Cobia Platforms located in Production Area VIC/L05 in Bass Strait. The repair involves the Seven Eagle dive support vessel laying a 150mm flexible pipeline between the Halibut and Cobia risers and making the associated tie-ins. The campaign is expected to take place in December 2018 and last approximately 10 days and will involve divers and ROV activities. 
The Environment Plan also covers leaving the redundant CBA300 pipeline in-situ until future decommissioning plans are developed or the pipeline is incorporated into a new or revised operations Environment Plan. Until decommissioning is completed, maintenance activities on the pipeline will continue be undertaken. The Cobia Pipeline Repair Project Environment Plan will cease when the new or revised operations Environment Plan is accepted by NOPSEMA.

Other Details
Locations Gippsland
Commonwealth waters adjacent to VIC
Titles (or other instruments) VIC/PL15
Current Documents (Finalised)
EP Document


Decision notifications




Location map