Banner image

Greater East Spar Installation and Commissioning

Activity type Significant modification of a petroleum pipeline
Activity subtypes
Lifecycle Classification Development
Submitted by Santos WA Southwest Pty Limited
Submission date 13 April, 2017
Subtype New
Decision date 29 June, 2017
RMS ID 3993
Status Finalised
Outcome Accepted
Link to previously accepted EP
Contact

Ms Libby Howitt
Chief Environmental Advisor
Quadrant Oil Australia Pty Ltd
Level 9, 100 St Georges Terrace
PERTH  WA  6000
+61 8 6218 7100
HSE.Regulatory@quadrantenergy.com.au

Location map (click to enlarge)
Location map - Activity: Greater East Spar Installation and Commissioning  (refer to description)
Description


Quadrant  Energy operates  the  Varanus  Island  oil  and  gas  production  and infrastructure facilities located offshore Dampier. Oil and gas is supplied to Varanus Island from a number of offshore petroleum reservoirs via several subsea pipelines.
The Halyard gas field is located approximately 65 km west of Varanus Island, and currently comprises the Halyard-1 well connected via a flowline to the East Spar subsea infrastructure, from where gas is transported 65 km via pipeline to the East Spar gas plant on Varanus Island.
Quadrant is proposing to install additional infrastructure to connect another well, Spar-2, to the existing Halyard subsea facilities. The Spar-2 well is located approximately 1.7 km west-southwest of the existing Halyard-1 well, and was completed in December 2010 but was not connected. To complete the connection, Greater East Spar infrastructure must be installed.  Installation activities are expected to commence in Quarter 3, 2017, and run for up to 60 days. 

Other Details
Locations North West
Commonwealth waters adjacent to Western Australia
Titles (or other instruments) WA-21-PL
Current Documents (Finalised)
EP Document


Decision notifications




Location map