Woodside Energy Julimar Pty Ltd (Woodside), proposes to undertake the following activities for the Julimar Development Phase 2:
• Drill and develop four production wells, connected to a six-slot manifold (‘JULA’).
• Construct an approximately 22 km production flowline and control umbilical extension between the JULA manifold and the existing Brunello Crossover Manifold (BRU-XOM).
• Install and pre-commission subsea hardware and flowline.
The Petroleum Activities Program will be carried out using a moored semi-submersible MODU, pipelay vessel, installation vessels and a variety of support vessels, and is anticipated to commence in Q4 2019 and be completed in 2022. The proposed activities are located within Production Licence WA-49-L, approximately 185 km offshore from Dampier on the north west coast of Western Australia, with the closest landfall being the Montebello Islands, approximately 48km to the south.