Activity - East Spar Inspection and Removal

Activity details
Organisation Santos WA Southwest Pty Limited
Project Varanus Island Hub
Activity types Significant modification of a petroleum pipeline
In-force EP 4678
Submission date 16 November, 2018
Outcome Accepted
Acceptance date 11 December, 2018
Locations North West
Start date 01 February, 2019
Stop date 04 March, 2019
Lifecycle Classification Operation & Production
Please note: activity start and stop dates are based on notifications provided by the titleholder.

Titleholder contact
Tim Robinson
Phone: +61 8 6218 7100

Activity Description

A revision of the Environment Plan has been submitted for activities to occur in 2019.
Quadrant Oil Australia Pty Ltd (QOA) is the registered operator for Petroleum Production Licence WA-13-L in offshore Commonwealth waters on the North West Shelf (NWS) of Western Australia (WA). QOA is 100% owned subsidiary of Quadrant Energy Australia Ltd (Quadrant). Quadrant proposes to install infrastructure required to perform intelligent pigging (inspection) activities of the East Spar system, and remove flowlines and associated infrastructure which are at the end of design life and no longer used in production.
 The East Spar Inspection and Removal activities will be carried out using a Dive Support Vessel (DSV) or Installation Support Vessel (ISV).  Installation of infrastructure is required to allow intelligent pigging activities to inspect the East Spar system, prior to removal of flowlines and associated infrastructure of the East Spar 1, 3 and 6 Production System.

Location map (click to enlarge)
Location map - Activity: East Spar Inspection and Removal (refer to description)

EP Documents

EP Document A680805 (2.41 MB)
Decision notifications A647339 (165 KB)